Front Street Tender Awarded
At its Regular Meeting dated December 11, 2023, Council unanimously approved the submitted low tender bid from Cassidy Construction in the amount of $4,517,312.97 - a savings of over $600,000 from when the project was originally tendered in January 2023. . Council had previously given Staff direction to allow the Contract to commence as early as January 2, 2024. Cassidy Construction has informed staff that they may start as early as January 15, 2024 pending weather and supply availability. Works will be substantially completed Fall 2024 with final restoration in Spring 2025.
As always, during the work, construction equipment will be on site and noise / dust will be factors during the construction. Please use caution walking and driving around construction equipment and crews. Please adhere to all guidance provided by traffic control persons and temporary construction signage to ensure a safe and successful project.